Hazardous waste landfill site lined with geosynthetic linings

Hazardous waste landfill site lined with geosynthetic linings

Product News Tuesday, February 2, 2010: Engineered Linings (Pty) Ltd.

Client                                                  Chrome International South Africa

Project                                               Hazardous Landfill site, Newcastle

Liner Specification                         Primary Liner - 2,0mm HDPE
                                                            Secondary Liner - GCL
                                                            Slope Re-inforcement - Geomesh
                                                            Intermediate Drainage - Geonet
                                                            Tertiary Liner - 1,0mm HDPE

Size                                                    357 200m²

Consultants                                     Steffen Robertson & Kirsten (SRK)

Application Details

Chrome International is a joint venture between Bayer SA and Sentrachem. The plant produces sodium dichromate crystals, sodium dichromate solution and chromium trioxide, and the waste stream generated requires secure storage to prevent pollution.

The hazardous (H:h) landfill was the first phase to be developed for Chrome International South Africa and exceeds existing DWAF legislation, meeting proposed future standards.

A sophisticated double liner system incorporating a leak detection layer was installed to provide the required security. Photograph shows partial completion of one slope with the white GCL awaiting the final 2,0 mm thick HDPE liner.

See photo - On the far slope all 5 layers can be seen. Moving left to right is 1,0mm HDPE, Geonet, Geomesh, GCL and finally 2,0mm HDPE. In the foreground, Geotextile is used for protection of a temporary walkway.

The composite lining installation to Phase 1 took approximately 6 weeks to complete. It was however filled far quicker than anticipated and Phase 2 had to be constructed and lined during the first half of 2000. We installed the same composite lining system in both phases.

OTHER LINED LANDFILLS

Aloes -  Cell 2 (H:H)
Bellville South - Cells 5,6&7 (GLB+)
Bulbul Drive - Phases 1,2A, 2B & 2C (1&2) (H:h)
Brugspruit Hazardous Waste Lagoon (H:h)
Holfontein - Cells 1A,3,4,5,6A & 6B (H:H)
Mariannhill - Cells 1, 2A, 3 & 4A (GLB+)
Mossgas Hazardous Waste pond No. 3 (H:H)
Shongweni - Cells 1, 2, 3 & 4 (H:h)
Umlazi - Northern Site (H:h)
Vissershok Waste Management Facility Cells 2 & 3 (H:H)
Vissershok/ CMC - Cell 2, 3, 4 (H:h)
Coastal Park Landfill (CMC) - Phase 2A , 2B, 2C, 2D(GLB+)
Buffelsdraai Landfill (GLB+)
Kupferberg Landfill - Windhoek, Namibia
DCLM Landfill - Kwazulu Natal